RedTeam Go - How do I create an Owner Change Order NOT from a Request for Pricing?

This article describes options for creating a CO.

Changes > Change Orders > Owner CO Tasks>Create: Owner A CO

Type the name of the Change Order.

Click Create CO.

Click Add Item 1 Description.

Type the description for the change order.

Click Add Item 1 Cost, select the cost code and click on Add Cost Item(s).

Input the raw Owner Price. Markups will be applied using default settings from Administration > Default Rates. Each markup rate can be changed per line item on the change order.

Input the Sub Price. In the case of a .S (Subcontractor) expense type code, this should be the amount that you will award the Subcontractor.

Click Save.

Click Return to Change Order List in the dark gray bar.

To execute the Owner Change order, check the box next to Owner Change Order.

Click on Owner Change Order Tasks and click Sign Checked Owner Change Order.

Select Recipients and click I Agree.

Are you sure you want to sign this Owner Change Order? Click OK and Close Window.

RedTeam Go will automatically email the Owner the change order with a link in the email to click to view/sign the change order.