HAND SIGNED LIEN RELEASE
If your General Contractor is using the Hand Signed Lien Release option, upon their approval of your Subcontractor invoice, you will receive an email with a PDF attachment of the Lien Waiver. You will take the Lien to be signed/notarized, then click the link to upload your Lien back into RedTeam Go.
1.) When the Bill is Submitted this message will pop up on the screen:
2.) When the Bill is Approved by Project Manager, you will receive the following e-mail with PDF lien document attached and a link to upload the notarized lien:
3.) Print your lien Document> Sign> Notarize
4.) Scan your notarized document
5.) Then pick one of these methods to upload:
Click the link in the Lien E-mail to upload the notarized Lien on the Go Portal
Log in> Go to Billing Icon> select project name> click Sign Lien at the left side of your screen> Click Upload Lien next to Bill.
* This message on the Billing portal will change to when the PM has approved the bill and the upload link will be available here as well as in the Lien Release drawer.
6.) Choose File and click Submit File
7.) This message will appear in the Billing area until your lien release document is Approved.
8.) You will receive this message to indicate that the lien has been approved and you can create the next pay application under the Billing Icon.
DIGITAL LIEN RELEASE
If your General Contractor is using the Digital Lien Release, you will be prompted to sign the Lien Waiver at the same time you Submit your Subcontractor Invoice. Click "I Agree"
If you skip the above steps to sign and return your Lien Waiver, you can return to the Subcontractor RedTeam Go site, and Click on Lien Releases > Select Project.
Then you will click on Sign Lien if the General Contractor is using Digital Liens> choose "I Agree"> click OK and close window.