RedTeam Go - How does a superintendent issue RFIs?
RedTeam Go - How does a superintendent issue RFIs?

This article will teach superintendents how to issue RFIs

Updated over a week ago

To create an RFI you will go toTasks > RFI > Create RFI.ClickAdd RFI.

This will open the RFI Creation Screen (below)

Add RFI Form Cells

  • Subject – RFI Name

  • RFI Date – Date RFI is created

  • Due Date – Date Response is Required

  • Question – Text area for question

  • Submitted By – Party that creates RFI

  • Answerer -Party to Answer RFI. If the intended recipient does not appear in list, add them to the Project Information Page

  • Affects Cost – Select Yes or No. Defaults to No selection

  • Affects Schedule – Select Yes or No. Defaults to No selection

  • Bidding RFI – Selecting Yes will identify this as a Bidding RFI next the RFI number and on the reports

  • Specifications – Select from Planroom or free type

  • Drawing – Select from Planroom or free type

  • Cost Code – Select from cost code list

  • Distribution – To Copy Contacts on the RFI, start typing and the system will suggest matches. If the contact is not yet in your database, the system will prompt you to enter with a Quick Add feature.

  • Available contacts /Selected contacts - These are contacts already on the job that will receive a notification every time something happens with the RFI.

  • Attachments – Drag & Drop or Click to Browse for files

  • Reminders – Check box to send Automated Reminders 24 hours prior

  • Save – Saves any updates to the RFI Form

  • Save and Submit – Saves information, then sends the RFI out to recipient and distribution list via e-mail. Answers and Responses are collected via the e-mail link and posted in the View/Manage Answer menu choice.