RedTeam Go - Why Create A Potential Change Order (PCO) Before A Change Order

This article discusses the PCO to CO process.

With Potential Change Order (PCO) you can create an “wish list” of items that can be pulled into the project via a change order. The process is started with a PCO because when a change order is created, all change orders have to be APPROVED in order since they affect the contract amount. Therefore, by starting with a PCO, the pricing is presented to the Owner, the Owner can approve / reject each item proposed in the PCO and the approved items can be pulled into a change order with one click. By having the PCO approved first, the change order process is not held up because you already have approval.