RedTeam Flex - Indicated Outcome Report (IOR)

The Indicated Outcome Report is updated in real time to provide a full picture of the outcome based off the Schedule of Values (SOV).

Updated over a year ago

The Indicated Outcome Report is updated in real time to provide a full picture of the outcome based off the Schedule of Values (SOV). For our clients who manage CMAR projects this is a powerful tool to review with their customers the expected outcome by comparing the projected Contract Value against the Estimate at Complete.


1. Generating the Indicated Outcome Report (IOR)

The Indicated Outcome Report (IOR) can be generated for projects that have linked their SOV to the Budget (CMAR Projects). The report is run from the "Contract" tab of a project. There are options to change the columns displayed, export, and print the report.

To generate the report, users must have the permission ViewIOR active for their role.

Steps:

  1. Open the project that the report will be run for.

  2. The selected project must have the "Link SOV to Budget" option activated to run IOR.

  3. Click on the "Contract" tab.

  4. Click on the "View" button and select "Indicated Outcome Report" from the list.

  5. In the top right corner are options to show or hide columns, print, and export the report.