Users can now filter by Critical Path and by Resource.
Viewing by Critical Path Only (items linked by red line) will hide the tasks that are not a part of the shortest path to project completion.
Critical Path only:
Viewing by Resource allows user to select the names of Subcontractors, Owner, Architect, Employees, etc. that are assigned to tasks as the responsible Resource in the Task Detail modal. Multiple contacts can be selected to display onscreen. Selecting to Print in Gantt chart format will display on those tasks on the printed Schedule.
Filtered to show just the Owner’s tasks: