Yes, you can add Child Tasks. Here’s how:
Click the Ellipse Icon > Select Add Cost Code Child.
Start to type and select the same cost code as the Parent code:
Check the Alias Box and add new description to the child task, (the parent cost code will list after the new description)
HINT: Remember that the Parent will become a group so you will need to add all Child Tasks needed to completed the Group on the Schedule (these Child Tasks will be tracked on the Daily Logs integration).
Enter Start Date and Task Duration
The Parent cost code will already be populated
Select the Group task you would like the new child to fall under (Note: the only choice will be the parent Group if it is the first child added).
Why isn’t the Cost code Box populated with the Parent Cost code already?
There is a second Child Task option called Add Cost Code Child which is to add DIFFERENT cost codes to a Group. Since Groups replace traditional Parents (same cost code only) and Summary bars, multiple cost codes, custom tasks and milestone can be included in them.